Delay Cost Clock · Formula v1.1.0

What does each day of delay actually consume?

Separate cash that leaves the owner from contribution that may be delayed or partly recovered. Then compare the cash burn with remaining contingency before urgency turns into a bad concession.

Local teaching model. Formula v1.1.0; all defaults are fictional.

Use actual commitments and contract dates; do not treat lost contribution as guaranteed revenue.

Clock and recurring cash

Opportunity cost and contingency

Contingency gate$12,852 more cash is needed before opportunity cost

Opportunity cost remains separate because delayed patients or work may be recovered, lost, or shifted; it is not the same as cash leaving today.

Recurring cash burn$95,852
One-time cash burn$27,000
Total cash burn$122,852
Unrecovered contribution scenario$55,195
Total economic delay cost$178,047
Economic cost per day$2,374
2.5 average months

The day count is converted with 30.4375 days per average month. Contract billing periods may differ.

$38,900 per month

Recurring commitments that continue during the modeled delay.

5.6 contribution months

Months of the stated mature contribution needed to equal total economic cost—not a payback promise.

Assign the mechanism

Permitting, owner decisions, contractor sequence, lender draws, landlord work, equipment, staffing, and credentialing create different remedies.

Controlling formula · v1.1.0economic delay cost = recurring cash burn + documented one-time cash burn + unrecovered contribution scenario

Cash burn and opportunity cost are never merged until both are shown separately. The model does not decide who is legally responsible or whether damages, insurance, rent relief, or financing extensions are recoverable.